@@ -6210,6 +6210,14 @@ Risks have always to be considered in any long term project planning due
\begin_layout Itemize
+\series bold
+Business risks
+\series default
+, involving the company developing the software.
+\end_layout
+
+\begin_layout Itemize
+
\series bold
Project risks
\series default
@@ -6224,312 +6232,744 @@ Technical risks
, involving the project implementation.
\end_layout
-\begin_layout Itemize
-
-\series bold
-Business risks
-\series default
-, involving the company developing the software.
-\end_layout
-
\begin_layout Subsection
Project Risks
\end_layout
-\begin_layout Itemize
-Risk: No estimations/schedules have been made before this project.
+\begin_layout Standard
+\align center
+\begin_inset Tabular
+
+
+
+
+
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Risk
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Probability
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Damage
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Possible solution
+\end_layout
+
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+No estimations/schedules have been made before this project.
A lack of experience in this area can lead to serious errors in evaluating
- development time –
+ development time
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: High
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+High
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: Studying previous works on a similar subject can be
- very helpful in this.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Studying previous works on a similar subject can be very helpful in this
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: Due to several overlapping tasks the team is involved into, the project
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Due to several overlapping tasks the team is involved into, the project
is very likely to suffer from schedule delays
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: High
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+High
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: A strict organization among the team components is
- fundamental.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A strict organization among the team components is fundamental.
This implies a constant cooperation between developers, in order to squeeze
- even the tiniest time slots available for this project.
-
+ even the tiniest time slots available for this project
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: A sudden growth in requirements can lead to a rush to meeting deadlines,
- jeopardizing the overall quality
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A sudden growth in requirements can lead to a rush to meeting deadlines,
+ jeopardizing the overall quality
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: Thinking with a broader mind on the first stages can
- be very helpful; however, the team should be care- ful against over-engineering
- (which can also paralyze the develop- ment)
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Thinking with a broader mind on the first stages can be very helpful; however,
+ the team should be careful against over-engineering (which can also paralyze
+ the development)
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: Collaboration issues can sometimes be crucial, especially when dealing
- with task divisions.
-
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+The team is very small (3 people) but homogeneous; if someone leaves or
+ gets ill then the remaining team would have serious repercus- sions
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Low
\end_layout
-\begin_layout Itemize
-Damage: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: Meeting often can be a solution, other than explicitly
- writing whose responsibility for each task is.
-
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+All team members must be able to cover all development sections and cooperate
+ effectively
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: The team is very small (3 people) but homogeneous; if someone leaves
- or gets ill then the remaining team would have serious repercus- sions.
-
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Collaboration issues can sometimes be crucial, especially when dealing with
+ task divisions
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Low
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_layout Itemize
-Damage: Catastrophic
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_layout Itemize
-How to deal with it: All team members must be able to cover all development
- sections and cooperate effectively.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Meeting often can be a solution, other than explicitly writing whose responsibil
+ity for each task is
+\end_layout
+
+\end_inset
+ |
+
+
+
+\end_inset
+
+
+\end_layout
+
+\begin_layout Standard
+\begin_inset Newpage newpage
+\end_inset
+
+
\end_layout
-\end_deeper
\begin_layout Subsection
Technical Risks
\end_layout
-\begin_layout Itemize
-Risk: A lack of previous experience in developing with Java EE can almost
- surely slow down the entire team, which has to study these new technologies
- first
+\begin_layout Standard
+\align center
+\begin_inset Tabular
+
+
+
+
+
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Risk
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: High
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Probability
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Damage
\end_layout
-\begin_layout Itemize
-How to deal with it: This has to be account in the first stages of planning
- and inserted in the project scheduling.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Possible solution
+\end_layout
+
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A lack of previous experience in developing with Java EE can almost surely
+ slow down the entire team, which has to study these new technologies first
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+High
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+This has to be account in the first stages of planning and inserted in the
+ project scheduling
+\end_layout
+
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+If the servers happen to be unreliable or in the case of more users than
+ expected, a significant downtime can seriously damage the whole projects
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: If the servers happen to be unreliable or in the case of more users
- than expected, a significant downtime can seriously damage the whole project
- –
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A scalable design of the overall architec- ture is essential, both in software
+ and in hardware choices
\end_layout
-\begin_layout Itemize
-How to deal with it: A scalable design of the overall architec- ture is
- essential, both in software and in hardware choices.
-
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+The application may be susceptible to security issues if not well designed
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: The application may be susceptible to security issues if not well-
- designed.
-
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+All modern standards in computer security guidelines must be followed, especiall
+y when dealing with the user input, which has to be correctly verified and
+ processed
\end_layout
-\begin_layout Itemize
-How to deal with it: All modern standards in computer security guidelines
- must be followed, especially when dealing with the user input, which has
- to be correctly verified and processed.
-
-\end_layout
+\end_inset
+ |
+
+
+
+\begin_inset Text
-\end_deeper
-\begin_layout Itemize
-Risk: Testing may prove difficult (for example, if several mocks are necessary)
+\begin_layout Plain Layout
+Testing may prove difficult (for example, if several mocks are necessary)
or highlight problems which are hard to solve, especially when doing integratio
-n testing or —even worse—validation.
-
+n testing or even worse validation
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Medium
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: All components must be unit tested as soon as possible,
- to eliminate serious bugs when they first appear; integration testing must
- be done according to the specifications contained in [5].
- A periodic check of requirements contained in [2] is also required.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+All components must be unit tested as soon as possible, to eliminate serious
+ bugs when they first appear; integration testing must be done according
+ to the specifications contained in [5].
+ A periodic check of requirements contained in [2] is also required
+\end_layout
+
+\end_inset
+ |
+
+
+
+\end_inset
+
+
+\end_layout
+
+\begin_layout Standard
+\begin_inset Newpage newpage
+\end_inset
+
+
\end_layout
-\end_deeper
\begin_layout Subsection
Business Risks
\end_layout
-\begin_layout Itemize
-Risk: Testing devices & infrastructure (PCs, several mobile phones, server
- rent) need to be purchased and configured.
+\begin_layout Standard
+\align center
+\begin_inset Tabular
+
+
+
+
+
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Risk
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Probability
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Damage
+\end_layout
+
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+
+\series bold
+Possible solution
+\end_layout
+
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Testing devices & infrastructure (PCs, several mobile phones, server rent)
+ need to be purchased and configured.
This is going to increase costs, that may be not sustainable if the company
- is too small.
-
+ is too small
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: High
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+High
\end_layout
-\begin_layout Itemize
-Damage: Catastrophic
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: Testing tools are to be clearly defined in [2], in
- order to avoid worthless spendings.
-
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Testing tools are to be clearly defined in [2], in order to avoid worthless
+ spendings
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: The company may find itself in serious financial trouble.
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+The company may find itself in serious financial trouble
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Low
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Low
\end_layout
-\begin_layout Itemize
-Damage: Catastrophic
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: A feasibility study together with the RASD must highlight
- the impossibility of starting a whole new project.
-
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A feasibility study together with the RASD must highlight the impossibility
+ of starting a whole new project
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: myTaxiService may violate some (future) laws related to taxi management.
-
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+PowerEnjoy may violate some (future) laws related to taxi management
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Low
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Low
\end_layout
-\begin_layout Itemize
-Damage: Critical
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Critical
\end_layout
-\begin_layout Itemize
-How to deal with it: A periodic check must be done in order to avoid legal
- consequences.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+A periodic check must be done in order to avoid legal consequences.
In the case of drastic changes, the whole team must work in order to adapt
- to the new regulations as soon as possible.
-
+ to the new regulations as soon as possible
\end_layout
-\end_deeper
-\begin_layout Itemize
-Risk: Another bigger company could acquire this company.
-
+\end_inset
+ |
+
+
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Another bigger company could acquire this company
\end_layout
-\begin_deeper
-\begin_layout Itemize
-Probability: Low
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Medium
\end_layout
-\begin_layout Itemize
-Damage: Marginal
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+Marginal
\end_layout
-\begin_layout Itemize
-How to deal with it: No preventive solutions are available.
- Note that this is not necessarily a negative thing.
+\end_inset
+ |
+
+\begin_inset Text
+
+\begin_layout Plain Layout
+No preventive solutions are available.
+ Note that this is not necessarily a negative thing
+\end_layout
+
+\end_inset
+ |
+
+
+
+\end_inset
+
+
\end_layout
-\end_deeper
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset