Section 4 done. Formatting fixes

This commit is contained in:
Giulio De Pasquale 2017-01-19 17:30:25 +01:00
parent 0db3108b9f
commit 0bbd835a84

View File

@ -658,6 +658,13 @@ http://www.qsm.com/resources/function-point-languages-table
\end_inset
\end_layout
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
@ -3532,6 +3539,13 @@ SLOC=46\cdot181=8326
\end_inset
\end_layout
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
@ -3820,31 +3834,43 @@ Schedule Estimation Now we can estimate the project duration with the following
0.31 ⇠ = 9.44 M onths
\end_layout
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
Tasks & Schedule
Tasks scheduling
\end_layout
\begin_layout Standard
The main tasks of this project are the following:
The main assignments of our project are:
\end_layout
\begin_layout Enumerate
Creation of the Requirement Analysis and Specification Document [2], which
explains in detail functional and nonfunctional require- ments, domain
assumption and goals of the application to be built.
Creation of the Requirement Analysis and Specification Document (
\series bold
RASD
\series default
).
\end_layout
\begin_layout Enumerate
Creation of the Design Document [3], which deals with the architecture and
the design shape of the application.
Creation of the Design Document (
\series bold
DD
\series default
).
\end_layout
\begin_layout Enumerate
Creation of the Integration Testing Plan Document [5], which con- tains
integration testing strategy we intend to apply to the application.
Creation of the Integration Testing Plan Document (
\series bold
ITPD
\series default
).
\end_layout
\begin_layout Enumerate
@ -3852,13 +3878,12 @@ Creation of the Project Plan, this document.
\end_layout
\begin_layout Enumerate
Preparation of a quick presentation, using slides, (⇠ 10 min) of the previously
mentioned documents to our client.
Creation of a set of slides to present our work to the client.
\end_layout
\begin_layout Enumerate
Development of the entire application and the preparation of the unit tests.
Development of the system and the preparation of the unit tests.
\end_layout
@ -3868,23 +3893,46 @@ Running of integration testing on the application.
\end_layout
\begin_layout Standard
For the first tasks the activities were already given along with correspond-
ing deadlines for the submission of needed documents.
Starting from the im- plementation, instead, no schedule was given so,
according to the COCOMO estimation performed and described in 2, we expect
the implementation of the application to be complete in 9.5 months, around
the 15th of September 2016.
Regarding the integration testing, it will take place in the last month
of developement.
The development of the application started after the creation of the De-
sign Document and will be carried on in parallel with the rest of the tasks.
Tests will be run on the developing application in order to verify the
proper functioning of every new functionality added.
In Figure 3 you can find the dependency graph of every task, in Table 20,
The first four tasks were already completed within the given submission
deadlines.
Starting from step 5 onward, according to our COCOMO® estimation
\begin_inset Foot
status open
\begin_layout Plain Layout
see Section 3 for more details
\end_layout
\end_inset
, we expect to deliver a working implementation within
\series bold
TODO
\series default
months which corresponds to
\series bold
mid-TODO.
\series default
The development started just after the submission of the Design Document
and continued simultaneously with the rest of the tasks; the integration
testing will take place in the last month.
In the meantime, tests will be run all along the entire development process
to verify the proper functioning of every added feature.
\series bold
In Figure 3 you can find the dependency graph of every task, in Table 20,
instead, you can find the schedule of every task.
Also the Gantt chart for the project is provided in Figure 4.
\end_layout
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
Resource Allocation
\end_layout
@ -3912,6 +3960,13 @@ This section is meant to show the way our available resources are allocated
24, 25, 26, 27.
\end_layout
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
Risks
\end_layout
@ -4254,6 +4309,13 @@ How to deal with it: No preventive solutions are available.
\end_layout
\end_deeper
\begin_layout Standard
\begin_inset Newpage newpage
\end_inset
\end_layout
\begin_layout Section
Appendix
\end_layout